Based on the F&A rate pdfagreement, for projects funded on or after 07/01/09, the rates will be:


Activity
Period
On-Campus Off-Campus*
Research 7/1/09 – until renegotiated 52.5% 26%
Instruction 7/1/09 – until renegotiated 52.5% 26%
Other Sponsored Activities 7/1/09 – until renegotiated 36% 26%

Rates are applied to a Modified Total Direct Cost (MTDC) base i.e., to all costs except equipment (stand alone items with a useful life of a least 1 year and a unit cost of at least $5,000); alterations and renovations; patient care costs; tuition; rental of off-site facilities; subcontract and subgrant costs in excess of $25,000.

*Off-campus rate applies to those projects (a scope of work or activity with a separate budget and accounting) for which 50% or more of the salary and wages are incurred in facilities not owned and controlled by the University and for which rent is allocated as a direct cost to the project.

See University Policy Regarding F&A Rates

Components of the Research and Development F&A Cost Rate


Component
Building Use/Depreciation 4.9%
Equipment Use/Depreciation 4.2%
Interest 2.0%
Operations and Maintenance 13.3%
Library 2.1%
Administration (General, Departmental, and Sponsored Projects) 26.0%
TOTAL 52.5%